The London District Catholic School Board wants to build St. Thomas’s new Catholic high school on farmland at the northeast corner of Southdale Line and Shaw Valley Drive. Plans filed with the City on November 16th show St. Lucy Catholic Secondary School, a two-storey school with 36 classrooms for 826 students, and the board expects it to open in September 2028.
The board has bought the 19.3-acre property with room for two schools, a high school and an elementary school, but only the high school is funded. The province approved $41.6 million for it in January 2025, not counting the cost of land.
The City’s Site Plan Control Committee will hold a public hearing on the plans on Thursday, December 3rd, at 2:30 p.m., online through Microsoft Teams. The committee will consider whether to approve the plans and drawings for the site. The full application, including the drawings and a traffic study, is on the City’s current planning applications page, and the hearing instructions have the link to join. You can also phone in and listen live at 437-703-4416, conference ID 951 439 392#, or call Planning and Building Services at 519-633-2560 with questions.
The plans put the high school on the north part of the property. A football field with a six-lane running track, metal bleachers and six sports light poles fills the east side, beside existing homes along that property line. The site plan shows 190 parking spaces, a bus drop-off lane and a space marked for a future addition to the school.

The south part of the lot is held for the elementary school, and no building is drawn there yet. The traffic study still plans for it, with 424 students, 42 staff and a child care centre inside. The board asked the province for both schools in 2024, including an 88-space child care centre at the elementary school, but only the high school was approved. Notes on the site plan say the board sent the elementary school back to the Ministry of Education for funding in September 2025. It was left out again when the province approved three more of the board’s schools in April 2026, and the notes say the ministry has given “no timeline” for funding it.
The high school’s plans show two driveways, both on Shaw Valley Drive: a full in-and-out driveway and an exit-only lane joining the existing roundabout. An entry-only driveway off Southdale Line appears only in the traffic study’s plan for both schools, beside the future elementary school. The high school is planned for 18 full-size school buses and five specialized vans. The traffic study, done for the board by the firm EXP and counting both schools, estimates 586 car trips in the busiest morning hour and 585 in the busiest afternoon hour.
The study expects nearby intersections to work acceptably in 2033, five years after opening, with one exception: drivers on Glenwood Street turning left onto Sunset Drive would face long delays, worst in the afternoon. A traffic light there is not warranted, so the study recommends the City keep watching that corner. It also recommends retiming the lights where Sunset Drive meets Southdale Line, Shaw Valley Drive and Parkside Drive, a new sidewalk along the school’s frontage on Southdale Line and Shaw Valley Drive, and Community Safety Zone signs.
For students on foot, the study finds two spots that qualify for a pedestrian crossover: where Shaw Valley Drive comes into the roundabout from the south, and on Southdale Line east of Shaw Valley Drive. On Southdale Line it favours the kind with push buttons and flashing lights. It says it is too early to tell whether a crossing guard will be needed, since the schools are not built yet. But if the simpler crossover without push buttons and lights goes in on Southdale Line instead, the study recommends a guard there.
An archaeological dig on the property in the summer of 2025, done for the board, found a thin scatter of stone artifacts from about 8,900 to 9,800 years ago, left by Indigenous people who likely used the spot to make and repair tools. The archaeologists concluded no further work is needed at that site. In September, the board’s property and planning committee heard that staff were still working with the province’s Ministry of Citizenship and Multiculturalism on archaeological approvals.
The same committee heard that staff were preparing the design documents the Ministry of Education must check before the job can go to tender, aiming to submit them in the last three months of 2026. The board expects to tender the work in the first three months of 2027, if the ministry agrees to let it proceed. Earlier this year the board moved the expected opening up a year, from September 2029 to September 2028, and in June trustees approved the name St. Lucy.
Which students will go to St. Lucy is still to be decided. St. Joseph’s Catholic High School is the only existing high school the board expects the new school to affect, and an advisory committee is to recommend the new school’s boundary by June 2027. The board’s plan starts with a first report laying out at least two boundary options, one of them recommended by staff, and the report goes to the affected school community for comment. At least one public meeting follows between January and March 2027, and trustees make the final decision after the committee reports. That first report was expected at the board in November, but it is not on the agenda for trustees’ November 23rd meeting. The next board meeting is December 14th.
Sources: City of St. Thomas, current planning applications (SPC 13-26: notice, application, drawings, traffic study, archaeological assessment), LDCSB report, “St. Thomas Secondary School Boundary Review” (May 25, 2026), LDCSB, “Coming Soon: Two New High Schools and an Elementary School” (January 27, 2025).
By Anthony Zruna · About the LocVox Newsroom